To comprehensively enhance the teaching environment across our campus and optimize classroom facilities, we will continue to upgrade the remaining classrooms, following the initial renovations carried out during the winter vacation. This upgrade project will feature the installation of advanced LED screens (replacing traditional projectors), interactive whiteboards, and in-class recording systems, all aimed at creating a more modern and intelligent teaching and learning space for our faculty and students.
I. Renovation Schedule
The project will officially commence on February 14, 2025, and is expected to be completed by April 16, 2025.
To minimize disruption to regular teaching activities, the construction work will primarily be scheduled for weekends.
II. Detailed Classroom Renovation Plan
No. |
Classroom Number |
Construction Schedule |
---|---|---|
1 |
W1-102 |
Feb. 15-16; Apr. 19-20 |
2 |
W4-202 |
Feb. 15-16; Apr. 19-20 |
3 |
E3-202 |
Feb. 22-23; Apr. 12-13 |
4 |
W2-201 |
Feb. 22-23; Mar. 29-30 |
5 |
E1-147 |
Mar. 1-2 |
6 |
E4-101 |
Mar. 1-2 |
7 |
E1-150 |
Mar. 8-9 |
8 |
E1-149 |
Mar. 8-9 |
9 |
E2-228 |
Mar. 15-16 |
10 |
W4-101 |
Mar. 15-16 |
11 |
E1-102 |
Mar. 22-23 |
12 |
E1-201 |
Mar. 22-23 |
13 |
W1-222 |
Mar. 29-30 |
14 |
E1-122 |
Apr. 5-6 |
15 |
E1-134 |
Apr. 5-6 |
16 |
E1-101 |
Apr. 12-13 |
III. On-Site Contact Information
Contact: Jimmy LI, (020) 8833 9383
IT Service Hotline: (020) 8833 0101
IT Service Mailbox: gzit@hkust-gz.edu.cn
We sincerely apologize for any inconvenience that the renovation work may cause to your teaching and learning activities. Your understanding and support are highly appreciated. We will coordinate the construction progress to the best of our ability to ensure timely completion and the prompt return of classrooms to normal use. Should you have any questions or require assistance, please feel free to contact us.
Information Technology Department (ITD)
February 14, 2025